Displaying 126 - 150 of 200
Title Project Type Project Phase Planned Start Date Planned End Date Status Council District Estimated Cost Fiscal Year Sort ascending Funding Source
DLTWTF Master Plan Task Order 013 Filter Improvements Water P3: Procurement Consultant/Contractor Selection Process 5 $45713000.00 2024 PIPES
Downtown Core Complete Streets (Tampa St, Florida Ave, and Brorein St Resurfacing) Transportation P2: Design 90% Design Completion 5 $1900000.00 2024 Transportation Impact Fees
Copeland Park Pump Station Stormwater Engineering P3: Procurement Right-of-Way Acquisition 7 $325000.00 2024 Stormwater Improvement Fee
Hydrangia, West of Central Stormwater Engineering P5: Closeout Closeout 7 $150000.00 2024 Stormwater Improvement Fee
Morris Bridge Filter Roof Retro – COOP Site Water P2: Design 90% Design Completion 7 $43000000.00 2024 PIPES
Neighborhood Improvements- West Riverside Heights Transportation P2: Design 30% Design Completion 6 $2000000.00 2024 Local Option Gas Tax
4801 Neptune Way Stormwater Engineering P2: Design 30% Design Completion 6 $500000.00 2024 Stormwater Improvement Fee
Gunlock PS Generator Addition Wastewater P4: Construction Construction in Progress $650500.00 2024 PIPES
FY20 CIP Water Main Improvements Design-Build_15th St – GMP5 Water P1: Planning Planning 5 $7453750.73 2024 PIPES
Bayshore Pumping Station Rehabilitation Wastewater P2: Design 60% Design Completion 4 $6400000.00 2024 PIPES
Floribraska Ave (Tampa St to 9th St) Transportation P3: Procurement Project Startup 5 $2213390.00 2024 Multiple Funding
Golf View Flood Relief Water P2: Design 60% Design Completion 4 $2442041.73 2024 PIPES
Sulphur Springs Pumping Station Design Build Wastewater P2: Design 30% Design Completion 5 $19700000.00 2024 PIPES
Gandy Park South and A. J. Palonis Park Improvements Parks & Recreation P2: Design Planning 4 $2000000.00 2024 Other Agencies
Cal Dickson Greenspace Improvements Parks & Recreation P1: Planning Planning 6 $270000.00 2023 Community Investment Taxes
Training Burn Simulator and Skills Tower Fire P5: Closeout Final Inspection and Testing 5 $2571898.00 2023
Foundation for Tampa's Neighborhoods Project-Wastewater Improvements for Forest Hills Area Wastewater P4: Construction Construction in Progress 7 $4700000.00 2023 PIPES
Dazzo PS Relocation Wastewater P5: Closeout Closeout 6 $1271500.00 2023 PIPES
Downtown Interchange Wastewater Collection System Rehabilitation by CIPP Lining Wastewater P4: Construction Construction in Progress 5 $600000.00 2023 PIPES
Rocky Point Dr Complete Streets (South of Courtney Campbell Causeway) Transportation P5: Closeout Closeout 6 $798400.00 2023 Transportation Impact Fees
Waters Ave Gravity Sewer Rehabilitation Wastewater P4: Construction Construction in Progress 6 $1382767.00 2023 PIPES
Kid Mason Community Center Renovations Parks & Recreation P4: Construction Construction in Progress 5 $2623356.00 2023 Community Redevelopment Agency
East/West Columbus Drive Water P5: Closeout Closeout 5 $1438509.21 2023 PIPES
Sidewalks- 9th St (Bougainvillea Ave to Linebaugh Ave) Transportation P5: Closeout Closeout 5 $85000.00 2023 Sidewalk In-Lieu Fees
Sidewalks- 12th St. Sidewalk for Sulphur Springs K-8 Transportation P5: Closeout Closeout 5 $35000.00 2023 Sidewalk In-Lieu Fees