All Capital Improvement Projects

This is list of our Capital Improvement Projects to learn more visit our Capital Improvement Projects landing page.

Displaying 1 - 25 of 200
Title Sort descending Project Type Project Phase Planned Start Date Planned End Date Status Council District Estimated Cost Fiscal Year Funding Source
109th St Pumping Station Force Main Extension Wastewater P3: Procurement Consultant/Contractor Selection Process 7 $480000.00 2024 PIPES
122nd Ave Pumping Station Rehabilitation Wastewater P3: Procurement Consultant/Contractor Selection Process $1260000.00 2025 PIPES
131st St and Florida Ave Collection System Rehabilitation Wastewater P5: Closeout Closeout $770000.00 2022 PIPES
14th St (Av Republica De Cuba) & 21st Ave Transportation P4: Construction Permitting/Submittals Approval 5 $350000.00 2024 Local Option Gas Tax
21st St and Palm Ave - Traffic Signal Replacement Transportation P2: Design 90% Design Completion 5 $600000.00 2024 Local Option Gas Tax
24th St. Corridor Improvements (Chelsea St. to Emma St.) Transportation P4: Construction Construction in Progress 5 $357560.00 2023 Local Option Gas Tax
24th Street (Hanna Ave to Sligh Ave) Transportation P2: Design 30% Design Completion 5 $685000.00 2024 Local Option Gas Tax
30th Street (Yukon St to Fowler Ave) Transportation P2: Design 90% Design Completion 7 $5700000.00 2027 Local Option Gas Tax
4801 Neptune Way Stormwater Engineering P2: Design 30% Design Completion 6 $500000.00 2024 Stormwater Improvement Fee
56th Street & Broadway Avenue Flooding Relief Stormwater Engineering P2: Design 60% Design Completion 5 $2000000.00 2024 Stormwater Improvement Fee
7th Ave Water P2: Design 30% Design Completion 5 $12076333.00 2025 PIPES
Adalee Pumping Station Rehabilitation Wastewater P3: Procurement Final Contract Review & Approval 5 $1046500.00 2024 PIPES
Armenia/Howard/Columbus Gravity Sewer Rehabilitation Wastewater P4: Construction Construction in Progress 5 $2200000.00 2023 PIPES
Armory Gardens Water P2: Design 90% Design Completion 6 $1172467.83 2024 PIPES
Ballast Point PS FM Extension Wastewater P5: Closeout Closeout 4 $850000.00 2023 PIPES
Ballast Point Pumping Station Rehabilitation Wastewater P4: Construction Construction in Progress 4 $1478200.00 2025 PIPES
Bayshore Pumping Station Rehabilitation Wastewater P2: Design 60% Design Completion 4 $6400000.00 2024 PIPES
Beach Park Drainage Improvements Stormwater Engineering P5: Closeout Closeout 6 $1000000.00 2022 Stormwater Improvement Fee
Belmar Gardens Water P4: Construction Construction in Progress 4 $5581099.83 2022 PIPES
Belmar Gardens Gravity Sewer Rehabilitation Wastewater P4: Construction Construction in Progress 4 $1000000.00 2023 PIPES
Bermuda Blvd Complete Streets and Seawall Transportation P1: Planning Planning 5 $15000000.00 2027 Local Option Gas Tax
Brorein St Bridge (#105501) Phase 1 Structural Rehabilitation Transportation P2: Design 90% Design Completion 4 $9220000.00 TBD Local Option Gas Tax
Brorein St Bridge (#105501) Phase 2 Mechanical/ Electrical Rehabilitation Transportation P2: Design 90% Design Completion 4 $9930000.00 TBD Local Option Gas Tax
Cal Dickson Greenspace Improvements Parks & Recreation P1: Planning Planning 6 $270000.00 2023 Community Investment Taxes
Cass St Bridge (#105502) Electrical/Mechanical Rehabilitation Transportation P2: Design 90% Design Completion 5 $6930000.00 TBD Local Option Gas Tax