Primary Details
Description
Restoration and stabilization of the spring run/basin and living shoreline along the Hillsborough River.
Community Benefits
Resiliency and Sustainability: expand/enhance native vegetation and habitat, improve water quality, mitigate storm impacts, and protect infrastructure.
Project ID
1002316
Department ID
PR-20002
Project Type
Status
Project Phase
Construction Fiscal Year
2026
Multi Year Project
Yes
Council District
6
Neighborhood
Schedule and Costs
Project Phase
Planning
Design
Procurement
Construction
Closeout
Current Phase:
Design
Planned End Date
Funding Source
Multiple Funding
Estimated Cost
$700,000
Funded Project
Yes
Contract Number
TBD