Rocky Point Dr Complete Streets (South of Courtney Campbell Causeway)

Primary Details

Description

This project provides for safety and multimodal improvements.

The City proposes to mill and resurface, as well as correct areas of ponding stormwater along Rocky Point Drive from the Courtney Campbell Causeway to the south end extent for an approximate length of 1,900 feet. The City also proposes to add a sidewalk on the east side at Island Club and on the west side from Bay Club Circle to the Courtney Campbell Causeway. 

Community Benefits

Complete Streets & Safety Improvements

Contact Info

Contact Name
Jolanta Olbinska, P. E.
Contact Phone
813-274-8122
Project ID
TRANS20063
Department ID
TRANS20063
Project Type
Status
Project Phase
Construction Fiscal Year
2023
Multi Year Project
Yes
Council District
6

Schedule and Costs

Project Phase
Planning
Design
Procurement
Construction
Closeout
Current Phase: Closeout
Planned Start Date
Planned End Date
Funding Source
Transportation Impact Fees
Estimated Cost
$798,400
Funded Project
Yes
Phase Firm Phase Cost Funding Source Scheduled Start Scheduled Finish
Design Pennoni $95,424 City of Tampa (Complete Streets) 2022 2022
Construction $365,000 City of Tampa (Complete Streets) 2022 2023
Photo of cars travelling on Rocky Point Dr with ponding in roadway

Photo of Rocky Point Dr with cars in queue and stormwater ponding.