Ballast Point Pier Sunrise

Temporary Road and Lane Closure S MacDill Ave to begin August 7, 2024 for Utility Construction

Posted Date

TRAFFIC ADVISORY —Utility Construction

Roads Affected: S MacDill Ave (W Gandy Blvd - W Marlin Ave)

Dates: August 7, 2024 to August 8, 2024

Time: Daily, 9am - 4pm

Closure Type: Full Road Closure on August 7th

Northbound Lane Closure and Sidewalk Closure (east side) on August 8th

Permit: ROW-24-0001099 & ROW-23-0000912

Contact: Debbie Herrington, P.E., Transportation ROW Engineer
City of Tampa Mobility Dept / ROW Permitting
(813) 274-3104, Debbie.Herrington@tampagov.net