Lamb Canal Rehabilitation & Flood Relief

Primary Details

Description

This project provides relief for frequent and extreme flooding and to address bank erosion of the canal and ditches draining the watershed. the Lamb Canal Rehabilitation and Flood Relief project is being pursued and will include improvements to Lamb Canal between Westshore Blvd, and Manhattan Ave.and Emerson Ditch between Lamb Ave. and Bay-to-Bay Blvd.

The project is currently at a 60% design status. Upon completion, the project will relieve flooding along local and collector roadways thereby improving traffic safety, and water quality draining to Lake Dundee and Tampa Bay, as well as provide for a low-maintenance and resilient drainage system.

Community Benefits

Flooding Relief

Contact Info

Contact Name
Yvette Pullara
Contact Phone
813-274-8092
Project ID
1001171
Department ID
SW50006
Project Type
Project Phase
Construction Fiscal Year
On Hold
Multi Year Project
Yes
Council District
4
Neighborhood

Schedule and Costs

Project Phase
Planning
Design
Procurement
Construction
Closeout
Current Phase: Design
Funding Source
Stormwater Improvement Fee
Estimated Cost
$11,000,000
Funded Project
Yes
Budget Year
2022
Location

27.917513304781, -82.522533807684