Primary Details
Approximately 9,529 Linear Feet of water mains ranging from 4 to 12 inches in diameter will be replaced and upgraded. The project area and the streets impacted by this project are shown on the attached map.
Note: This is a supporting project related to South Howard Flood Relief.
Information related to the main project is located at:
https://www.tampa.gov/project/sw40007
The South Howard Water Improvement Project will improve the City of Tampa’s water distribution system by replacing the existing water mains and increasing the capacity of the system. This project will replace the aging water mains in this area with new and larger diameter water mains, improving water pressure and water quality while reducing the number of service interruptions that might have been caused by main breaks or leakage. It will also improve our ability to serve a growing population.