Interbay Blvd (Manhattan Ave to Tanker Way)

Primary Details

Description

This project provides for operational improvements by widening for a right turn lane.

Roadway improvements at Interbay Blvd between S Manhattan Ave and Tanker Way will include the construction of an additional right-turn lane on eastbound Interbay Blvd and the realignment of the travel lanes between Manhattan Ave and Tanker Way. These improvements will help reduce congestion and traffic delays.

The current roadway layout at Interbay Blvd includes a single eastbound right-turn lane onto Tanker Way, an access point for MacDill Air Force Base. The vehicles entering MacDill Air Force Base must be processed at the existing checkpoint creating a queue. The single right-turn lane has insufficient storage for vehicles entering MacDill Air Force Base resulting in the queue extending onto the thru lanes on Interbay Blvd. The proposed additional right-turn lane will provide additional storage and reduce congestion on Interbay Blvd.

Community Benefits

Congestion Mitigation

Contact Info

Contact Name
Robert C. Hatton, P.E.
Contact Phone
813-274-1289
Project ID
1001929
Department ID
TRANS20046
Project Type
Status
Project Phase
Construction Fiscal Year
2024
Multi Year Project
No
Council District
4
Neighborhood

Schedule and Costs

Project Phase
Planning
Design
Procurement
Construction
Closeout
Current Phase: Closeout
Funding Source
Transportation Impact Fees
Estimated Cost
$135,000
Funded Project
No
Budget Year
2022
Phase Firm Cost Funding Source Scheduled Start Scheduled Finish
Design DRMP $69,952 Impact Fees FY 2019 FY 2021