43rd St Ditch Rehabilitation

Primary Details

Description

Project area is located just west of the Tampa Distribution Center located at 1212 N. 50th Street as in identified as the 43rd Street Drainage Improvements because of the nearest downstream crossing. Work involves approximately 700 feet of concrete slope stabilization of an existing ditch and all miscellaneous and appurtenant work.

Community Benefits

The ditch alignment and sandy soils have caused heavy erosion in some embankment areas, causing continuous maintenance issues and the ditch to widen beyond its existing drainage easement limits. The rehabilitation involves embankment reconstruction and hardening to insure long-term future stability, reducing maintenance activities and reducing potential damage to adjacent parcels. The ditch bottom will remain open to allow for natural infiltration

Contact Info

Contact Name
Yvette Pullara
Contact Phone
813-274-8092
Project ID
1000751
Department ID
SW250001
Project Type
Project Phase
Construction Fiscal Year
2025
Multi Year Project
No
Council District
5
Neighborhood

Schedule and Costs

Project Phase
Planning
Design
Procurement
Construction
Closeout
Current Phase: Construction
Planned Start Date
Planned End Date
Funding Source
Stormwater Improvement Fee
Estimated Cost
$2,280,000
Funded Project
No
Contract Number
24-C0041
Location