Design and construction of approximately 16,300 LF of stormwater culverts with associated laterals, inlets, interconnections to existing stormwater system, associated utility conflict resolution relocations, transportation elements, water main replacement upgrades and sustainability treatment elements. The project will also include certain transportation elements as well as the replacement of approximately 11,700 LF of water mains not in the same corridors as the proposed stormwater infrastructure

Community Benefits

Flooding Relief/ Water Quality Improvement

Contact Info

Contact Name
Albert Calloway
Contact Phone
813-630-3902
Project ID
1001151
Department ID
SW40003
Project Type
Project Phase
Construction Fiscal Year
2022
Multi Year Project
Yes
Council District
6
Neighborhood

Schedule and Costs

Project Phase
Planning
Design
Procurement
Construction
Closeout
Current Phase: Construction
Planned Start Date
Planned End Date
Funding Source
Stormwater Improvement Fee
Estimated Cost
$30,000,000
Funded Project
Yes
Contract Number
19-C-00012