FY20 CIP Water Main Improvements Design-Build_W Chelsea St Transmission – GMP 5

Primary Details

Description

The W Chelsea St Transmission project will improve the City of Tampa’s water distribution system by replacing the existing water mains. It will also improve our ability to serve a growing population. Approximately 7,909 Linear Feet of water mains ranging from 6 to 24 inches in diameter will be replaced and upgraded.

Community Benefits

This project will replace the aging water mains in this area with new water mains, improving water pressure and water quality while reducing the number of service interruptions that might have been caused by main breaks or leakage.

Contact Info

Contact Name
Rynaldo Deshauteurs
Contact Phone
813-274-7221
Project ID
WTR-20-0005.3-W Chelsea St Transmission
Department ID
WTR-20-0005.3-W Chelsea St Transmission
Project Type
Project Phase
Construction Fiscal Year
2025
Multi Year Project
No
Council District
6
Neighborhood

Schedule and Costs

Project Phase
Planning
Design
Procurement
Construction
Closeout
Current Phase: Design
Funding Source
PIPES
Estimated Cost
$7,827,102
Funded Project
Yes
Location

27.98504657853, -82.459413774944

Project Location