Howard F. Curren AWTP Master Plan Improvements, Phase 2, Design-build Amendment No. 1

Primary Details

Description

This project provides for the design and equipment purchase of the Return Sludge Pump Stations No. 1, No. 2 and No. 3 electrical system improvements at the Howard F. Curren AWTP. The project will include replacement of the motor control centers, switchgears, variable frequency drivers, lighting panels and miscellaneous electrical components.

Community Benefits

The treatment plant project will restore the plant’s reliability by replacing aging equipment and will include improvements to reduce vulnerability to extreme weather events and sea level rise. The project will also enhance the treatment plant processes with modern technology which will increase the plant’s treatment and operating efficiency.

Contact Info

Contact Name
Charlie Lynch
Contact Phone
8132748916
Project ID
1001865.4B
Department ID
WW1001865.4B
Project Type
Project Phase
Construction Fiscal Year
2025
Multi Year Project
No
Council District
5
Neighborhood

Schedule and Costs

Project Phase
Planning
Design
Procurement
Construction
Closeout
Current Phase: Procurement
Planned Start Date
Planned End Date
Funding Source
PIPES
Estimated Cost
$3,350,000
Funded Project
Yes
Location

27.923391169885, -82.437168388189

Project Location