Boats in Harbor

Traffic Advisory Water Utility Relocation: September 18, 2023 to March 29th, 2024

Posted Date

TRAFFIC ADVISORY -- Water Utility Relocation

Roads Affected: Floribraska Avenue from North Tampa Street to Nebraska Avenue

Construction period: September 18th 2023, thru March 29th 2024

Time: 9:00 AM to 4:00 PM

Phase 1: North Nebraska Avenue to North Elmore Street

Dates: Sep 19, 2023 - Oct 23, 2023

Phase 2: North Elmore Street to North Jefferson Street

Dates: Oct 23, 2023 - Dec 1, 2023

Phase 3: North Jefferson Street to North Florida Avenue

Dates: Dec 4, 2023 - Jan 5, 2024

Phase 4: North Florida Avenue to North Tampa Street

Dates: Jan 8, 2024 - Jan 19, 2024

 

Permit: CWS-23-0000766

 

See road closures at https://www.tampa.gov/roadclosures

See capital projects at https://www.tampa.gov/projects

See active permits at https://www.tampa.gov/permits