View each step below to obtain additional information about each stage in Commercial Generator permit process
Application
- Building Miscellaneous
Fees
Do you want to get an estimate of your permit fee? Use this link to go to the Fee Calculator.
Document Review
- Site Plan or Survey
- Generator location
- Surrounding Trees
- Property Lines
- Building Plans
- Concrete Pad Plan
- Electrical Plan (Riser)
- Sizing Report
- Generator Product Data Sheets
- Site Plan or Survey
Inspection
- BLD-Pre-Construction Inspection
- BLD-Underground Drainage System
- PLB-Stormwater System
- ELE-Underground Rough-In
- Fire-Final
- PLB-Final
- ELE-Final
- BLD-Final
RFC - Ready for Completion
Use the Project Coordination Status Report (PCSR) on this page to get information on pending items like Open related permits, Open Conditions, Fees due and/or Inspections due to complete your project.
To see if your project qualifies for the Fast Pass-Same Day application, visit the Fast Pass page
Above information is provided as a guide. Additional information may be required, please consult with our Client Facilitation team at: csdhelp@tampagov.net