- BLD-Pre-Construction Inspection
- BLD- Foundation / Footer
- BLD-Stem Wall
- BLD- Above Grade Slab
- BLD-Pilasters/Fill Cells/ Columns
- BLD-Wall or Roof Sheathing
- BLD-Insulation – Walls
- BLD – Insulation – Ceilings
- BLD – Framing
- PLB-Water Service
- PLB-Underground Rough-in
- PLB-Sewer
- PLB – Tub Set
- PLB-Rough-In
- PLB-Final
- MEC-Rough-In
- MEC-Final
- ELE-Rough-In
- ELE-Final
- BLD-Site Final
- BLD-Final
Above Inspections list is provide as a guide. Additional inspections may be required, depending on the project scope of work. Consult with your Building Inspector.
Select an option below to obtain additional information about each stage in Residential Accessory Structure permit process
Application
Fees
Plan Review
Inspections
RFC (Ready For Completion)